Project updates

Update 13 October 2017
 
We will be completing our work to temporarily reinstate our working area at the junction with Cove Road and Southwood Road and hope to remove the traffic lights here next Tuesday (17 October). We will need to return here as we haven’t been able to remove equipment needed to pressure test the new pipe.
 
Next week we will be continuing our work at Cove Brook before we move onto our connection work at Prospect Road.
 
For the safety of the public and our workforce, traffic lights will be in place for two weeks on Prospect Road from Monday 23 October to connect our new pipeline to the existing network.

Update 6 October 2017

Today we successfully carried out work to connect our new pipeline to the existing network in Cove Road.

Traffic lights will now remain in place at the junction with Southwood Road until Friday 20 October. We know this is inconvenient but we will be removing equipment used to pressure test the new main while we are here so we will not need to come back to this section.

Once this work has been completed, we will be moving to the junction of West Heath Road and Prospect Road to lay the final section of pipe and connect it to the existing network.

For the safety of the public and the crew on site, temporary traffic lights will be in place between Monday 23 October and 3 November.

Thank you to local residents and motorists for your patience.

Update 29 September 2017

This week we have been working on a footpath next to Cove Brook and we will need to return here at a later date.

Traffic lights remain in place on Cove Road at the junction with Southwood Road. We are waiting for a piece of equipment needed for our connection to arrive and we plan to do this work on Friday (6 October) and then reinstate this area.

We will also be starting to test the new pipeline next week.

Update 21 September 2017

We have now finished laying the new section of our pipe along Fleet Road and the road is now open. We will need to return here for a short period at a later date to remove equipment which helps us pressure test the new pipe.

Traffic lights are currently in place on Cove Road at the junction with Southwood Road. They will remain here until Friday 13 October to allow us to connect the new pipe laid to our existing network. We are currently getting a piece of equipment needed for this connection specially made which has delayed us in this area.

Once this work has been completed, we will need to temporarily return to West Heath Road to connect the new section of pipe laid underneath Cove Brook and connect the new pipeline to our existing network in Prospect Road. We will keep you updated on the planned dates for these pieces of work.

Update 14 September 2017

Our lane closure remains in place along Fleet Road and we still hope to complete this section of work by Monday 18 September despite the number of unchartered utilities.

Once this section of work is complete, we will need to return to carry out work to connect the new pipeline to the existing network on Cove Road at the junction with Southwood Road. This work will be carried out under three-way traffic lights.

Update 1 September 2017

Our lane closure is currently in place along the section of Fleet Road off West Heath Roundabout. 

The gang on site has come across a number of unchartered utilities which has slowed progress this week. As a result, we now expect to be working on this section until Monday 18 September.

We are sorry for this delay and we will keep you updated on our progress.

Traffic is now flowing along West Heath Road. We will need to return to the brook to connect the new pipe to the existing network at a later date. We will update you when we have a date for this work confirmed.

Update 21 August 2017

The water levels dropped enough for us to successfully lay our new pipe beneath Cove Brook last week. We hope to lift the road closure currently in place between the junctions of Giffard Drive and Glebe Close as soon as possible. We will keep you updated on this.

From tomorrow we will be moving into the Fleet Road lane from West Heath Roundabout. While this work takes place, no traffic will be able to come into Fleet Road however traffic will be able to exit from Fleet Road to go to West Heath Roundabout. While this section is closed, motorists should use Southwood Road and the A327 to return to Fleet Road.

We expect to be in this section until Sunday 10 September.

While this closure is in place, bus service 10 travelling from Farnborough towards Fleet will be diverted via Minley Road and Trunk Road. This means the bus stops opposite the Plough and Horses, Conway Drive and Ladywood Avenue will not be served. Buses running towards Farnborough will be unaffected. If you have any queries on the bus routes, Stagecoach can be contacted on 0345 121 0190 (option 1) or visit stagecoachbus.com.

We will need to return here at a later date to connect the new pipe.

Update 15 August 2017

Lane closures remain in place on West Heath Roundabout as we continue to lay our new pipe across the roundabout towards Fleet Road.

Work here is progressing well and we expect to move onto Fleet Road on Monday. While this work takes place a temporary road closure will be in place and motorists should follow the diversion route via Southwood Road and A327.

While this closure is in place, bus service 10 travelling from Farnborough towards Fleet will be diverted via Minley Road and Trunk Road. This means the bus stop opposite the Plough and Horses, opposite Conway Drive and Opposite Ladywood Avenue will not be served. Buses running towards Farnborough will be unaffected. If you have any queries on the bus routes, Stagecoach can be contacted on 0345 121 0190 (option 1) or visit stagecoachbus.com.

We hope to start laying our pipe underneath Cove Brook from tomorrow (16 August) but this will be dependent on water levels. A temporary road closure will be in place between Giffard Drive and Blunden Road until this section is complete.

Update 28 July 2017

The traffic lights at the junction of Cove Road and Southwood Road have now been removed and the inside lane of the West Heath Roundabout moving towards Cove Road is temporarily closed.

Next week we will be laying the pipe across this lane and the traffic island before moving across the road and into the inside Lane for Fleet Road. Motorists will need to use the middle lane on West Heath Roundabout and move back across to the Fleet Road access lane if travelling via Fleet Road.

Next week we also hope to begin our work to lay a new section of pipe beneath Cove Brook. This was due to take place this week but the water levels remain too high for this work to be carried out. We now hope to start this work at the middle of next week. The temporary road closure between Giffard Drive and Blunden Road will remain in place while this work takes place.

We would like to thank local residents and motorists for their patience. We know roadworks are frustrating but we are working as quickly as we can to get the new pipe laid.

Update 14 July 2017

We have continued to lay our new main along West Heath Roundabout, moving under the railway bridge. Over the weekend and on Monday, we will be reinstating the area we have been so far and we are hoping to set up three-way traffic lights at the mini roundabout on Cove Road.

After closely liaising with Rushmoor Borough Council, it was agreed that one of the Willow trees that is along the route at Cove Brook will unfortunately have to be removed to allow us to lay the new pipe here.

The decision to remove this tree was not taken lightly but following a specialist survey, the future stability of the tree could not be guaranteed.

We understand this tree is a prominent feature of the local landscape and arrangements will be made for a replacement tree to be planted within the Cove brook area. This will be carried out in autumn which is the best time to plant it.

Work to remove the tree will begin on Monday (17 July).

Update 5 July 2017

Our work continues to progress well along West Heath Road, we are currently working within a lane closure between Blunden Road and West Heath Roundabout.

We have also moved into a single lane closure around West Heath Roundabout that will run for a fortnight.

Bus services 10, 409 and 410 have been diverted via Fernhill Road and Mayfield Road and the Yo-Yo has resumed its normal route.

From week commencing 17 of July works will start to install our pipe within Cove Brook, along West Heath Road. We envisage being in this area for some time to carry out the extensive works needed.

So far we have laid 972 metres of pipe on the scheme.

Thank you to local residents and motorists for your ongoing cooperation.

Update 26 June 2017

Our work continues to progress well along West Heath Road and we are currently working within our rolling road closure between Blunden Road and West Heath Roundabout.

We have also moved into a single lane closure around West Heath Roundabout that will run for a fortnight.

Bus services 10, 409 and 410 have been diverted via Fernhill Road and Mayfield Road and the Yo-Yo has resumed its normal route.

So far we have laid 948 metres of pipe on the scheme.

Update 19 June 2017

Our work continues to progress well along West Heath Road, we are currently working within our rolling road closure between Blunden Road and West Heath Roundabout. We have also moved into a single lane closure around West Heath Roundabout that will run for another week.

Bus services 10, 409 and 410 have been diverted via Fernhill Road and Mayfield Road and the Yo-Yo has resumed its normal route.

So far we have laid 918 metres of pipe on the scheme.

Update 13 June 2017 

We have now started work to lay our new pipe around West Heath Roundabout before we lay the small section in Fleet Road. While this section of the project takes place lane closures will be in place along the roundabout.

Thank you to local residents and motorists for your patience and we apologise for any inconvenience this section of work may cause.

Update 7 June 2017

We are currently working within our rolling road closure between Blunden Road and West Heath Roundabout.

We expect to move into a single lane closure around West Heath Roundabout early next week.
So far we have laid 903 metres of pipe on the scheme.

Thank you to local residents and motorists for your ongoing patience and cooperation while this important project takes place.

Update 25 May 2017

Our work continues to progress well along West Heath Road, we are currently working within our rolling road closure between Glebe Road and Blunden Road. We expect to remain here next week.

Bus services 10, 409 and 410 have been diverted via Fernhill Road and Mayfield Road and the Yo-Yo has resumed its normal route.

So far we have laid 768 metres of pipe on the scheme.

Update 28 April 2017

Our work continues to progress well along West Heath Road, we are currently working within our rolling road closure between Giffard Drive and Glebe Road. We expect to remain here next week.

Bus services 10, 409 and 410 have been diverted via Fernhill Road and Mayfield Road and the Yo-Yo has resumed its normal route.

So far we have laid 586 metres of pipe on the scheme.

Update 13 April 2017

Our work continues to progress well along West Heath Road and our gang has laid the new pipe up to the junction of Giffard Drive.

We have completed the reinstatement of the previous road closure and will be moving the road closure to between Giffard Drive and Glebe Road.

Bus services 10, 409 and 410 will be diverted via Fernhill Road and Mayfield Road from Tuesday (18 April) and the Yo-Yo will resume its normal route.

So far we have laid 542 metres of pipe on the scheme.

Update 4 April 2017

Our work continues to progress well along West Heath Road and our contractors have laid the new pipe past the junction of Watts Road. We are currently awaiting reinstatement of the road so we can move the rolling closure between the junctions of Watts Road and Giffard Drive.

So far we have laid 420 metres of pipe on the scheme.

Update 23 March 2017

Work has progressed well along West Heath Road and our contractors have laid the new pipe past the junction of Clouston Road. we are just awaiting reinstatement of the road so we can move the rolling road closure between the junctions of Clouston Road and Stuart Close.

So far we have laid 350 metres of pipe on the scheme.Update 23 March 2017

Update 10 March 2017

Our rolling road closure is still in place between the junctions of Beta Road and Clouston Road and work here is progressing well.

We hope to reach the junction of Clouston Road by the end of next week.

Thank you to local residents and motorists for your ongoing patience.

Update 27 February 2017

The gang has progressed well along West Heath Road and have laid the new pipe past the junction of Beta Road. This means the road closure is in now in place between the junctions of Beta Road and Clouston Road.

So far we have laid 114 metres of pipe on the scheme.

Thank you to local residents and motorists for your patience while this work continues.

Update 10 February 2017

The rolling road closure has now moved between the junctions of Romayne Close and Beta Road. We expect to be at this section of the road for a couple of weeks before moving the road closure along.

Update 6 February 2017

Work along West Heath Road has progressed well so far and we are pleased to say the new pipe has been laid up to the junction with Romayne Close.

We hope to reinstate the road within the current closure between the junction of Prospect Road and Romayne Close by Friday, before the rolling road closure moves along to between the junctions of Romayne Close and Beta Road.

Thank you to local residents and motorists for your ongoing patience and cooperation.

Update 31 January 2017

Last week we completed enabling works along West Heath Road before work begins to lay the new pipe. We have also set up a site compound at the junction Mayfield Road and Fernhill Road to allow us to store materials.

The road closure along West Heath Road is now in place between the junctions of Prospect Road and Romayne Close. We expect the road closure to be in place here until the middle of February before the working area moves along.

Update 19 January 2017

Bus services 10, 409, 410 and the Yo-Yo will be following the diversion route from Thursday 19 January before we start laying the new pipe along West Heath Road on Monday 23 January.

As a result the Yo-Yo service will use Prospect Road in both directions then take the usual route on Cherrywood Road and Wren Way before turning left on Mayfield Road where it will return via Prospect Road. Services 10, 409 and 410 will divert to serve Giffard Drive and Mayfield Road before resuming the normal route on Prospect Avenue.

We apologise for any inconvenience this may cause.

Update 17 January 2017

Our work to lay 1.3 kilometres of pipe along West Heath Road and a section of Cove Road and Fleet Road will start on Monday 23 January.

The first road closure will be located along West Heath Road between Prospect Road and Romayne Close. This means motorists should use Giffard Drive and Mayfield Road to access Prospect Road.

We will start setting up the site on Monday before we start laying the new pipe.

We have been working closely with Stagecoach Buses and the Yo-Yo bus service and services 10, 409 and 410 will be affected.

While West Heath Road is closed between Prospect Road and Giffard Drive, the Yo-Yo service will use Prospect Road in both directions then take the usual route on Cherrywood Road and Wren Way before turning left on Mayfield Road where it will return via Prospect Road. Services 10, 409 and 410 will divert to serve Giffard Drive and Mayfield Road before resuming its normal route on Prospect Avenue.

When work progresses to the west of Giffard Drive, the Yo-Yo will resume its normal route, but services 10, 409 and 410 will have to use Fernhill Road and Mayfield Road.

If you have any queries on the bus routes, Stagecoach can be contacted on 0345 121 0190 (option 1) or visit stagecoachbus.com.

West Heath Road leaflet

West Heath Road poster

Update 16 December 2016

Thank you to all local residents who came along to our drop-in session on Wednesday evening. Our project team valued all the feedback that was received.

We are currently finalising details with the local bus company but we will update residents when the diversion routes are confirmed.

Thank you in advance for your patience and cooperation. Regular updates on the progress of this important scheme will be available on this page.