Wednesday 11 October

Work is progressing well and we are currently laying around 100 metres of new pipe per week.

To date we have installed just under 750 metres of water main our of a total 1372 metres. Our works are currently located just past Cackle Street to the South of Nutley.

Thank you for your patience and cooperation.

Wednesday 27 September

To date we have laid 377 metres out of the total 1372 metres of new main. Work continues to head in a southerly direction along the A22 towards Maresfield.

Work is progressing well and we are currently on track to complete the scheme on schedule.

Thank you for your patience and cooperation.

Friday 8 September

Works are underway within the private field, just off of the A22, and two-way traffic lights have been put in place on the main road.

We have also begun digging the road in preparation for laying our first section of pipe.

Regular updates on the scheme will be available on this page.