Key Facts

Location: Arlington Reservoir

Work: Equipment installation

Starts: Monday 26 October

Duration: Approx. seven weeks

We’re planning to install specialist equipment to improve the connectivity of our water network at our Arlington Reservoir.

When will work start and how long will it take?

We’ll be starting work at our site on Monday, 26 October, 2026. We expect the project to take around seven weeks.

The majority of the work will take place in our own site, and so the impact will be minimal for most of the project.

However, there will be an impact on Station Road while we make connections to the existing network. To carry out this work safely, we’ll need temporary traffic lights on Station Road from Monday, 9 November, for approximately two weeks.

We’re sorry for any inconvenience this may cause. Our team will aim to complete the work as quickly as possible and clear the road.


Share this Article: