We’re always working to reduce the number of leaks and bursts we have across our network and ensure we continue to supply top quality drinking water.

With this in mind, we’re going to be making some improvements to the water network in the Ash Green area of Surrey.

What’s going to happen and when?

We’re going to install around 1.5 kilometres of water mains near the Ash Green and Flexford areas of Surrey.

This includes work in phases in Pound Farm Lane, Green Lane West and along the by-way leading to Beech Lane, with additional work required towards the end of the project in a small section of Ash Green Lane East.

Road closures will be required in both Pound Farm Lane and Green Lane West and because of this, there will be strictly restricted access to properties during our working hours.

We want to work with the community to try and minimise disruption as much as possible and we have met with local residents to gather information and establish any specific access and parking arrangements.

We have listened to the feedback from the residents and businesses in the area and we’ve adapted our plans to help minimise the impact of the works.

This includes limiting our working hours during the day approximately between 9am and 3pm in certain sections of road to try and reduce the impact on the local community, while looking to complete the work as quickly as possible to minimise disruption.

We’ll be using a mixture of drilling and open cut to lay the pipes, with progress likely to be slower while we are using the open cut method.

The planning for this project is underway and we’re currently aiming to start work in the first phase of work on Monday, 11 January 2027.

We expect this work to take approximately around 11 months in total. We’ll do our best to get the work done faster if we can.


We’re sorry for the disruption this work is going to cause; we know it’s inconvenient. We’ll do our absolute best to keep it to a minimum.

We’ll look to maintain access to homes and businesses during this work, where possible. There may be a wait occasionally if we’re working directly outside the entrance to a property just while our team makes the area safe to cross, or complete an element of work such as a concrete pour.

Rolling road closures will be in place for the safety of motorists, pedestrians and our work force.

Full details of the traffic management will be published on our website, once agreed with Surrey County Council’s Highways.


There may be a short interruption to supply when we connect our new pipes to the existing network. We’ll let those impacted know if this is going to happen at least 48 hours beforehand.

If you’d like to know more or you have any questions before the work starts, please contact us:

  • Call our advisors on 0333 000 0002
  • Email customerservices@southeastwater.co.uk

We’ll also be regularly posting news and other information on this page.