Key facts

Location: Mount Pleasant Road, Clay Hill Road and Free Heath Road, Hook Green

Work: Replacing just under 1.8 kilometres of water main

Starts: Monday 5 September

Duration: Approx. six months


We’re replacing just under 1.8 kilometres of water main to reduce the number of leaks and bursts we have across our network and ensure we continue to supply top quality drinking water to the local community.

When will work start, and how long will it take?

We’ll be starting work on Monday 14 September. We expect the work to take approximately seven months. We’ll do our best to get the work done faster if we can.


Will there be roadworks?

For the safety of the public and our team, work will be carried out under a mix of road closures and temporary traffic lights as follows:

  • Monday 14 September 2026: Mount Pleasant Road

Mount Pleasant Road will be closed for approximately 170 metres from the junction with Clay Hill Road. This will be for around eight weeks.

  • Monday 28 September 2026: Clay Hill Road

Clay Hill Road will be closed from the junction with Mount Pleasant Road to the junction with Furnace Lane (B2169) for around four months

  • Monday 4 January 2027: Junction of Clay Hill Road and Furnace Lane (B2169)

Two-way temporary traffic lights for approximately two weeks

  • Monday 4 January 2027: Free Heath Road

Free Heath Road will be closed from the junction with Furnace Lane (B2169) for approximately 160 metres. This will be for approximately two months

For each closure, a diversion route will be in place and signposted for the duration of the works. The route will also be available to view on this webpage.

FAQs

We do all we can to minimise disruption to the community when laying new water mains and always look to install pipes in locations which will cause the least disruption, such as grass verges and when in a road, as close to the verge as possible.

In the case of Hook Green, residents and businesses will still be able to access their property, but we will need closures or temporary traffic lights as follows:

  • Monday 14 September 2026: Mount Pleasant Road

Mount Pleasant Road will be closed for approximately 170 metres from the junction with Clay Hill Road. This will be for around five weeks.

  • Monday 28 September 2026: Clay Hill Road

Clay Hill Road will be closed from the junction with Mount Pleasant Road to the junction with Furnace Lane (B2169) for around four months

  • Monday 4 January 2027: Junction of Clay Hill Road and Furnace Lane (B2169)

Two-way temporary traffic lights for approximately two weeks

  • Monday 4 January 2027: Free Heath Road

Free Heath Road will be closed from the junction with Furnace Lane (B2169) for approximately 160 metres. This will be for approximately two months

For each closure, a diversion route will be in place and signposted for the duration of the works. The route will also be available to view on this webpage.


All of these services will still be able to access properties for the duration of our work. Ahead of work starting, we advise these services of our works. Our on-site team will work with providers.


As the work will require connections to the existing network, there will be a short interruption in supply. We will notify you well in advance when this is due to happen if you are impacted by a loss of supply.

Customers with additional needs be it a disability, mental health or financial concerns can sign up to our Priority Services Register to help us understand how we can help you. More information can be found at southeastwater.co.uk/priority

This dedicated scheme webpage will be updated as work progresses, but if you have any concerns during the work, the staff on site will be happy to answer any questions you may have.

If you would like to speak to us direct, please call our advisors on 0333 000 0002 or email us at customerservices@southeastwater.co.uk